Compared to new builds,
refits need a different
approach.
Especially with exhaust refits it is very important to start the refit with a professional planning. By taking this approach you can safe your company considerable time and money.
Based on our experience in designing and delivering all kinds of exhaust refits, we have come up with three tips that could be vital to your exhaust refit success.
To make all components fit properly and to deliver all components just on time, we need all required information as soon as possible.
On average the lead time of a complete exhaust refit will be approximately 24 weeks.
Especially with exhaust refits it is very important to start the refit with a professional planning. By taking this approach you can safe your company considerable time and money.
Based on our experience in designing and delivering all kinds of exhaust refits, we have come up with three tips that could be vital to your exhaust refit success.
1. Be early
It is imperative to contact us well
in time before the yacht arrives at
the yard.Our engineers are very creative in
finding space for all the new
components.To make all components fit properly and to deliver all components just on time, we need all required information as soon as possible.
On average the lead time of a complete exhaust refit will be approximately 24 weeks.
2. Get as much info as
possible
For us to design the optimal
exhaust system we would like to
have the engine room as build
drawing if available.
We also need all engine output data as extensive as possible.
If the refit includes an exhaust that will exit under the water line of the yacht, we also need a drawing of the wave patterns of the yacht at different speeds.
3. Check your data
Over time, a lot can change in a
super yacht.
Unfortunately not every change that has been made is always recorded properly.
Therefore we recommend to check all data available on accuracy.